Maintenance Completed the Week Of: 2019-05-27
Cut and trimmed all turf areas.
Raked debris and algae from pond and streams.
Trimmed and weeded Dalhousie entrance.
Weeded Danbury entrance.
Pressured washed gazebo and graffiti from pillars.
Expected to complete June 3rd – June 8th 2019:
Apply Flocculant to ponds and streams.
Mow and trim all grass areas.
Weed, prune and clean up Dalhousie entrance.
Remove excess water weed growth from Lessard stream.
Build up soil around stream liners to better support the liners.
Cleanup around Danbury entrance.
Complete fence repairs in preparation for staining.
Meet with City to review plan for replacing dead trees removed from around the pond and streams.
Upgrade pump discharge piping at Dalhousie Fountain in preparation for start-up once cement repair and epoxy has properly cured.